‘Scathing indictment’: Massey Tunnel replacement will cost $8.5 billion, more than double original estimate
The estimated completion time for the project has also been delayed almost a year, from December 2030 to September 2031, despite previous reports the timeline would remain the same
By Alec Lazenby
Last updated 1 day ago
You can save this article by registering for free here. Or sign-in if you have an account.

The Massey Tunnel replacement project will cost $8.5 billion, more than double the original estimate of $4.15 billion from 2021, Transportation and Transit Minister Mike Farnworth announced Monday.
Subscribe now to read the latest news in your city and across Canada.
- Unlimited online access to articles from across Canada with one account.
- Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on.
- Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
- Support local journalists and the next generation of journalists.
- Daily puzzles including the New York Times Crossword.
Subscribe now to read the latest news in your city and across Canada.
- Unlimited online access to articles from across Canada with one account.
- Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on.
- Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
- Support local journalists and the next generation of journalists.
- Daily puzzles including the New York Times Crossword.
Create an account or sign in to continue with your reading experience.
- Access articles from across Canada with one account.
- Share your thoughts and join the conversation in the comments.
- Enjoy additional articles per month.
- Get email updates from your favourite authors.
Create an account or sign in to continue with your reading experience.
- Access articles from across Canada with one account
- Share your thoughts and join the conversation in the comments
- Enjoy additional articles per month
- Get email updates from your favourite authors
Sign In or Create an Account
Farnworth also said the estimated completion time for the project has been delayed almost a year, from December 2030 to September 2031, despite saying in mid-June that the timeline would remain the same.
tap here to see other videos from our team.
‘Scathing indictment’: Massey Tunnel replacement will cost $8.5 billion, more than double original estimate Back to video
tap here to see other videos from our team.
Farnworth said the updated budget reflects market conditions, inflation, project scope, and the realities of delivering a project of this size and complexity.
“Major infrastructure projects around the world have experienced similar cost pressures, and it’s important that we provide British Columbians with transparent and realistic information as the project progresses.”
The announcement comes three weeks after the province fired original contractors Cross Fraser Partnership — a consortium of Bouygues Construction Canada, Fomento de construcciones y contratas Canada, and Pomerleau B.C. — after the two parties failed to reach a final agreement.
Last week, Prime Minister Mark Carney said Ottawa would cover a third of the cost of the project, up to a maximum of $3 billion. Premier David Eby said on the weekend a new budget estimate for the tunnel is expected soon.
A replacement for the aging Massey Tunnel, built in the 1950s, has been in the works for well over a decade. The B.C. Liberals, under then-premier Christy Clark, promised a new 10-lane bridge to replace the tunnel.
In 2017, the new NDP government under John Horgan scrapped the proposed bridge in favour of a new tunnel due to environmental impact concerns and objections voiced by Metro Vancouver officials.

-
Advertisement 1Story continues belowThis advertisement has not loaded yet, but your article continues below.
Delta councillor Dylan Kruger, who is seeking a mayoral seat this fall, said he wished the bridge project had been maintained because it would have been completed several years ago and cost much less.
“Former minister (Rob) Fleming was adamant that there was no cost escalation, that there were no changes in the timeline. The current minister, Mike Farnworth, as recently as last week, said that there was no change to the timeline for the delivery of this project,” said Kruger.
“This is a scathing indictment on what can only be described as generational mismanagement of this critical infrastructure project for our region and for our country.”
He said residents who moved to Delta in 2012 and 2013 after the promise of a bridge have had their jobs and lives impacted by the switch to a tunnel.
Ian Paton, Conservative MLA for Delta South, said Monday he expects the budget to increase as the project progresses, and the new tunnel could end up costing as much as $11 billion.
Paton said he doesn’t believe the project will be complete by September 2031.
“Here’s a government bragging about what a priority this tunnel is, and yet they don’t even have a contractor, they literally fired the contractor,” said Paton.
“They don’t have an environmental assessment, they must be just assuming somebody’s just going to hand it to them because they happen to be government. And the other thing is — who’s going to build this thing? They don’t even have a contractor yet, and yet they’re telling us what it’s going to cost and when it’s going to be built by.”