‘Scathing indictment’: Massey Tunnel replacement will cost $8.5 billion, more than double original estimate

‘Scathing indictment’: Massey Tunnel replacement will cost $8.5 billion, more than double original estimate

The estimated completion time for the project has also been delayed almost a year, from December 2030 to September 2031, despite previous reports the timeline would remain the same

Author of the article:

By Alec Lazenby

Published Jul 06, 2026

Last updated 1 day ago

3 minute read

You can save this article by registering for free here. Or sign-in if you have an account.

The estimated completion time for the Massey Tunnel replacement project has now been delayed almost a year, from December 2030 to September 2031, despite previous reports the timeline would remain the same. Photo by NICK PROCAYLO /PNG
Article content

The Massey Tunnel replacement project will cost $8.5 billion, more than double the original estimate of $4.15 billion from 2021, Transportation and Transit Minister Mike Farnworth announced Monday.

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account.
  • Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on.
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
  • Support local journalists and the next generation of journalists.
  • Daily puzzles including the New York Times Crossword.
SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account.
  • Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on.
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
  • Support local journalists and the next generation of journalists.
  • Daily puzzles including the New York Times Crossword.
REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.
THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account
  • Share your thoughts and join the conversation in the comments
  • Enjoy additional articles per month
  • Get email updates from your favourite authors

Sign In or Create an Account

or View more offers

Article content

Farnworth also said the estimated completion time for the project has been delayed almost a year, from December 2030 to September 2031, despite saying in mid-June that the timeline would remain the same.

Article content

We apologize, but this video has failed to load.
Try refreshing your browser, or
tap here to see other videos from our team.
‘Scathing indictment’: Massey Tunnel replacement will cost $8.5 billion, more than double original estimate Back to video

We apologize, but this video has failed to load.
Try refreshing your browser, or
tap here to see other videos from our team.
Article content
Article content

Farnworth said the updated budget reflects market conditions, inflation, project scope, and the realities of delivering a project of this size and complexity.

Article content
Article content

“Major infrastructure projects around the world have experienced similar cost pressures, and it’s important that we provide British Columbians with transparent and realistic information as the project progresses.”

Article content

The announcement comes three weeks after the province fired original contractors Cross Fraser Partnership — a consortium of Bouygues Construction Canada, Fomento de construcciones y contratas Canada, and Pomerleau B.C. — after the two parties failed to reach a final agreement.

Article content

Last week, Prime Minister Mark Carney said Ottawa would cover a third of the cost of the project, up to a maximum of $3 billion. Premier David Eby said on the weekend a new budget estimate for the tunnel is expected soon.

Article content

A replacement for the aging Massey Tunnel, built in the 1950s, has been in the works for well over a decade. The B.C. Liberals, under then-premier Christy Clark, promised a new 10-lane bridge to replace the tunnel.

Article content
Article content

In 2017, the new NDP government under John Horgan scrapped the proposed bridge in favour of a new tunnel due to environmental impact concerns and objections voiced by Metro Vancouver officials.

Article content
In 2021, a rendering of a new eight-lane immersed-tube tunnel to replace the George Massey Tunnel was released. The Massey Tunnel replacement project will cost $8.5 billion, more than double the original estimate of $4.15 billion from 2021, Transportation and Transit Minister Mike Farnworth announced Monday. PNG
Article content
Read More
  1. Advertisement 1
    Story continues below
    This advertisement has not loaded yet, but your article continues below.
Article content

Delta councillor Dylan Kruger, who is seeking a mayoral seat this fall, said he wished the bridge project had been maintained because it would have been completed several years ago and cost much less.

Article content

“Former minister (Rob) Fleming was adamant that there was no cost escalation, that there were no changes in the timeline. The current minister, Mike Farnworth, as recently as last week, said that there was no change to the timeline for the delivery of this project,” said Kruger.

Article content

“This is a scathing indictment on what can only be described as generational mismanagement of this critical infrastructure project for our region and for our country.”

Article content

He said residents who moved to Delta in 2012 and 2013 after the promise of a bridge have had their jobs and lives impacted by the switch to a tunnel.

Article content

Ian Paton, Conservative MLA for Delta South, said Monday he expects the budget to increase as the project progresses, and the new tunnel could end up costing as much as $11 billion.

Advertisement 1
This advertisement has not loaded yet.
Advertisement 2
Advertisement
This advertisement has not loaded yet, but your article continues below.
Article content

Paton said he doesn’t believe the project will be complete by September 2031.

Article content

“Here’s a government bragging about what a priority this tunnel is, and yet they don’t even have a contractor, they literally fired the contractor,” said Paton.

Article content

“They don’t have an environmental assessment, they must be just assuming somebody’s just going to hand it to them because they happen to be government. And the other thing is — who’s going to build this thing? They don’t even have a contractor yet, and yet they’re telling us what it’s going to cost and when it’s going to be built by.”